Bell v Scotts Electrical & Pronto Engineering: When TUPE Applies to a One-Man Organised Grouping

CM
Christopher Mallon BL
19 March 2026
TUPEService Provision ChangeOrganised GroupingAutomatic Unfair DismissalNorthern Ireland

Case Reference: Bell v Scotts Electrical Services Limited & Pronto Engineering Group Limited

Case Ref: 15177/24IT(IW)-DM | Tribunal: Industrial Tribunal (Northern Ireland) | Heard: 12–13 May 2025, Belfast | Judge: Employment Judge Wimpress

Outcome: Award of £31,962.46 against the second respondent (Pronto Engineering) for automatic unfair dismissal following a service provision change under the Service Provision Change (Protection of Employment) Regulations (Northern Ireland) 2006.

Claimant represented by: Christopher Mallon BL, instructed by Thompsons Solicitors (NI) LLP.


Background

Colin Bell had worked as an SSES Level 2 Software Engineer and ICA Technician since 1 June 1990 — a continuous employment spanning 33 years. His work centred on a contract between his employer, Scotts Electrical Services Limited (R1), and Northern Ireland Water (NIW). Under that contract, Northern Ireland was divided into nine geographical areas, and Mr Bell was based in Lisburn covering Areas 2, 3 and 4 (the South East, from South Belfast to Armagh).

In May 2023 NIW restructured its framework by splitting the nine areas into three Lots and inviting fresh tenders. Crucially, the framework documentation stated in terms that TUPE does apply (para 2.4.1) and required tenderers to confirm they had read and priced for all TUPE obligations as a pass/fail condition (para 7.3). R1 retained Lot 1 (Areas 1, 8 and 9). Pronto Engineering Group Limited (R2) was awarded Lot 2 (Areas 2, 3 and 4) — the very area Mr Bell had worked in for years.


The TUPE Dispute

R1 took the position that Mr Bell's employment automatically transferred to R2 on 11 December 2023 by virtue of a service provision change (SPC). R2 flatly rejected the transfer, contending that:

  1. Mr Bell was not assigned to an "organised grouping" dedicated to Areas 2, 3 and 4 — his allocation was mere happenstance based on where he lived.
  2. The data provided by R1 was incomplete and unreliable.
  3. Mr Bell did not perform on-call work, which R2 regarded as a central pillar of the new contract.
  4. The fragmentation of the NIW contract into three lots meant the pre- and post-transfer activities were not "fundamentally the same."

Mr Bell found himself in legal limbo: R1 said he was R2's employee; R2 said he was still R1's. He attended a meeting with R2, corresponded with both employers, and raised unresolved grievances. When he did not attend R2's premises on 11 December 2023, R2 argued this amounted to an objection to transfer. Neither employer paid him after that date.


The Legal Framework: SPC Five-Stage Test

The tribunal applied the five-stage framework from Enterprise Management Services Ltd v Connect-Up Ltd [2012] IRLR 190, EAT:

SPC Five-Stage Decision Flowchart
1
Identify activities of original contractor
R1 provided software system engineering to NIW: configuration, design, fault-finding, installation. ✓ Satisfied
2
Are activities fundamentally the same post-transfer?
Fragmentation into lots and on-call changes did not fundamentally alter the nature of the work. ✓ Satisfied
3
Organised grouping with principal purpose of carrying out client activities?
Mr Bell was a one-man intentionally organised grouping — not happenstance. R1 deliberately assigned him to Areas 2, 3 & 4. ✓ Satisfied
4
Do any exceptions apply?
No single-event, short-term or goods-supply exceptions in play. ✓ No exceptions
5
Is the individual claimant assigned to the grouping?
As the sole member of the grouping, assignment was self-evident. ✓ Satisfied

Key Findings

1. Happenstance vs Intentionality

The central battleground was whether Mr Bell's allocation to Areas 2, 3 and 4 was deliberate or coincidental. R2 argued it was happenstance — he simply worked near his home. The tribunal rejected this emphatically.

The evidence showed that R1's Director of Operations, Mr Mayne, deliberately and intentionally allocated Mr Bell to Lot 2. This was a conscious business decision, not a geographic accident. The tribunal drew on the distinction articulated in Eddie Stobart Ltd v Moreman [2012] IRLR 356: it is not enough that an employee happens to carry out the majority of their work for a particular client — the organisation must be intentional, with the principal purpose of servicing that client.

Mr Mallon's submissions drew the tribunal's attention to a critical analytical error in R2's case: R2 had conflated the question of whether there was an organised grouping with the separate question of whether the claimant was assigned to it. These are analytically distinct inquiries and must be approached individually.

2. The On-Call Issue

R2 placed considerable weight on the fact that Mr Bell did not perform on-call work. Under the new NIW contract, on-call was scored at 20 marks in the tender and R2 argued it was a fundamental pillar of the service.

The tribunal was unpersuaded. The evidence demonstrated that on-call work:

  • Had been performed by subcontractors under R1
  • Was required only one week in seven under the new contract
  • Could be — and was — covered by R2's own direct employees

The tribunal held that the method by which on-call work was delivered was a matter for the employing contractor. The fact that Mr Bell had agreed with R1 not to perform on-call work did not remove him from the organised grouping, nor did it mean the pre- and post-transfer activities were not fundamentally the same.

3. The Fragmentation Argument

R2 relied on Clearsprings Management Ltd v Anker [2009] to argue that the division of the NIW contract into three lots constituted fragmentation, taking the case outside the SPC provisions. The tribunal rejected this. The activities performed before and after the service change were the same — the geographic restructuring did not fundamentally alter their nature.

4. The "Rock and a Hard Place" Finding

One of the most practically significant passages in the judgment concerns R2's argument that Mr Bell's failure to attend its premises on 11 December 2023 amounted to an objection to transfer under Hay v George Hanson (Building Contractors) Ltd [1996] IRLR 427.

The tribunal refused to draw this inference. Mr Bell had:

  • Attended a meeting with R2
  • Corresponded diligently with both employers
  • Raised unresolved grievances

Both employers had effectively "washed their hands" of him. In those circumstances, the tribunal found it was not realistic to expect Mr Bell to present himself for work with R2. There was no direct evidence that his non-attendance was an exercise of his right not to transfer.


Key Events Timeline

Timeline of Key Events
DateEvent
Jun 1990Mr Bell begins employment (continuous service date)
2019Mr Bell transfers to R1 (Scotts Electrical) via TUPE when R1 wins NIW contract
25 May 2023NIW puts restructured three-lot framework out to tender; TUPE stated to apply
Nov 2023R2 (Pronto Engineering) awarded Lot 2 (Areas 2, 3 & 4); R1 retains Lot 1
1 Nov 2023R1 notifies R2 of TUPE candidate (Mr Bell) for Lot 2
7 Dec 2023R2 formally rejects TUPE transfer of Mr Bell in writing
8 Dec 2023R1 maintains TUPE applies; Mr Bell left in legal limbo
11 Dec 2023Transfer date — Mr Bell does not attend R2's premises; neither employer pays him
19 Feb 2024Mr Bell secures new employment (end of loss period)
12–13 May 2025Full hearing before Industrial Tribunal, Belfast
2025Judgment issued — £31,962.46 awarded against R2

The Award

Compensation Breakdown
Head of LossAmount
Basic Award (33 years' service; 19 yrs × 1.5 × £669 + 1 yr × £669)£19,735.50
Holiday Pay (1.83 days accrued)£314.76
Notice Pay (4 weeks × £860 gross)£3,440.00
Loss of Pension Contributions (9 weeks × £25.80)£232.20
Loss of Earnings (11 Dec 2023 – 19 Feb 2024; 9 weeks)£7,740.00
Loss of Statutory Rights£500.00
Total Award£31,962.46
No uplift was applied as both respondents had engaged with and held meetings with the claimant regarding the transfer. No future loss was claimed as Mr Bell secured new employment by 19 February 2024.

Practical Lessons for Employers and Employees

This case carries important lessons for anyone involved in a service provision change — whether as an outgoing contractor, incoming contractor, or employee caught in the middle.

For incoming contractors (transferees):

  • You cannot simply reject a TUPE transfer by disputing the data. The tribunal acknowledged that R2 was "entirely within its rights to perform due diligence and query the data" — but imperfect data is not a sufficient basis to refuse to accept the transfer. If you believe the data is wrong, challenge it through the proper process, not by unilaterally declining to employ the transferring employee.
  • Read the tender documents carefully. The NIW framework stated in terms that TUPE applied and required tenderers to confirm this as a pass/fail condition. R2's witnesses admitted they had no prior understanding of TUPE and relied entirely on legal advice received after the award. That is too late.
  • Do not conflate the organised grouping question with the assignment question. These are analytically distinct. The existence of an organised grouping is assessed by reference to the transferor's organisation. Whether the individual claimant is assigned to it is a separate inquiry.

For outgoing contractors (transferors):

  • Provide complete and reliable employee liability information. R1's data was criticised as incomplete and inconsistent. While the tribunal ultimately found in the claimant's favour, poor data quality creates unnecessary litigation risk and may expose the transferor to claims for failure to comply with Regulation 11 (employee liability information obligations).
  • Do not update TUPE information at the last minute without notifying the client. The late change to Mr Bell's TUPE documentation — removing on-call availability and narrowing his work location — was viewed with suspicion by R2 and scrutinised by the tribunal.

For employees:

  • A TUPE transfer occurs by operation of law. Your employer cannot simply decide it does not apply. If both employers wash their hands of you, document everything, raise grievances, and take legal advice promptly.
  • Failure to attend the transferee's premises is not automatically an objection to transfer. The tribunal refused to infer an objection from Mr Bell's non-attendance given the circumstances. Context matters.
  • Long service counts. Mr Bell's 33 years of continuous employment (preserved through previous TUPE transfers) produced a basic award of nearly £20,000 before any other losses were added.

Key Cases Referenced

CasePrinciple
Enterprise Management Services Ltd v Connect-Up Ltd [2012] IRLR 190, EATFive-stage SPC test
Eddie Stobart Ltd v Moreman [2012] IRLR 356, EATOrganised grouping must be intentional, not happenstance
Ceva Freight (UK) Ltd v Seawell Ltd [2013] CSIH 59Single employee can constitute organised grouping
Rynda (UK) Ltd v Rhijnsburger [2015] EWCA Civ 70Single employee organised grouping confirmed by Court of Appeal
Churchill Dulwich Ltd v Metropolitan Resources Ltd [2009] IRLR 700Additional functions by new contractor unlikely to negate SPC
Clearsprings Management Ltd v Anker [2009]Fragmentation may take case outside SPC — rejected on facts here
Hay v George Hanson (Building Contractors) Ltd [1996] IRLR 427Objection to transfer can be by words or deeds — rejected on facts here

This case analysis is provided for general information only and does not constitute legal advice. If you are involved in a TUPE dispute — whether as an employer or employee — Christopher Mallon BL accepts instructions and can advise and represent you from the outset.

Continue reading

Share this post

Have a question about this topic?

Christopher Mallon BL is an employment barrister and is happy to discuss your matter in confidence.